Maria — Maplewood area (070)

8.4 kW DC · Installed March 2024 · PSE&G territory

The Install

What got put on the roof

Install summary — system size, utility, ZIP3, panel count
ItemDetail
System size8.4 kW DC
Panel count (est.)21 panels — assuming 400 W modules
InstalledMarch 2024
UtilityPSE&G
LocationZIP 070xx (New Jersey)
Production

Predicted vs actual production

The PVWatts number is what we used pre-install. The observed number is what the meter actually counted.

NREL PVWatts predicted vs observed (utility metered) annual production
SourceAnnual production
NREL PVWatts prediction10,584 kWh
Observed (utility data)10,847 kWh
Delta +2.5% — over the prediction
SREC Income

What the SRECs paid out

NJ SREC-II / ADI in PSE&G territory — each MWh produced earns one SREC, sold quarterly into the NJ market.

10.84 MWh

SRECs registered through the homeowner’s NJ GATS account for the trailing 12-month window. One MWh = one SREC.

$848

First-year SREC-II payout. NJ’s administratively determined incentive currently sets $76–95/MWh for 15 years — this study’s number reflects what cleared.

Bill Impact

Before vs after the install

Monthly utility bill before solar versus estimated post-install bill
WindowAverage monthly bill
Before solar$245
After solar (est.)$50 — baseline service + non-offset usage
Monthly savings$195 — before SREC income

Post-solar bill is a conservative $50/month estimate covering the utility delivery charge and seasonal non-offset usage. Real-life results vary month to month with weather and household load.

Homeowner quote

“I expected the savings. I didn't expect Chris to actually answer the phone on a Sunday when my inverter threw an error code.”

— Maria, PSE&G homeowner

Notes from the project

Maria’s 8.4 kW PSE&G install came in over the production model and tracked exactly to the SREC-II registration timeline we planned at intake. Maplewood is dense Bergen/Essex circuit, so I ran the suitability map before signing and confirmed the address sat on a non-saturated section — saved us a 6-week interconnection delay several of her neighbors weren’t so lucky to avoid.

Methodology

How I measure these numbers

  • Production: pulled from the homeowner’s utility net-metering portal (export kWh out of the meter back to the grid + self-consumed kWh from a Sense / inverter API where available). Partial-year installs are annualized in 12-month windows starting at permission-to-operate (PTO).
  • SREC payout: the homeowner’s NJ GATS account quarterly statement. Reported figure is the first full 12-month window post-registration. NJ SREC-II / ADI in PSE&G territory.
  • Predicted production: the NREL PVWatts v8 number we used in the original quote — same azimuth, tilt, and system loss inputs your installer would file with the utility.
  • Before-bill: 12-month average from the utility account history pulled at intake. After-bill is an illustrative $50/month estimate covering delivery charges and non-offset usage; actual months vary with weather and household load.
  • Privacy: ZIP3 only (never ZIP+4), first name only, photo only with the homeowner’s written permission.

Want Your Numbers Tracked This Way?

Every install I broker gets the same predicted-vs-observed tracking treatment. Run the calculator with me and I’ll show you what to expect from your roof.

Twelve years on rooftops. Free consultation, no pressure, no obligation.
Get My Free Estimate